GB-Edinburgh: Girdle Ness Lighthouse - Major Refurbishment and Upgrade

Northern Lighthouse BoardcontractContracts FinderRef BIP875932797SME suitableclosed
View buyer

Estimated value

£1.0m

Awarded value

Suppliers

0

Lots

1

0 awarded

Published

22 Jul 2024

Deadline 29 Aug 2024

Description

Decommission and remove the obsolete electrical operating / monitoring system, cubicles, chargers, battery, domestic electrical system, etc., in compliance with the WEEE (Waste Electrical and Electronic Equipment) Regulations 2013 Decommission the existing engine and dismantle. Strip out exhausts, ventilation equipment and ducting along with other mechanical accessories. Decommission and demolish all DGPS infrastructure Principal Contractor is expected to test the existing 'HCL' fall arrest system and re-certify it before use. Principal Contractor is to install a new electrical optic / monitoring system which must be tested to ensure compliance with current electricity at work regulations BS 7671. De-mobilise site and clear all surplus project materials and plant, with the disposal of excess project materials to appropriate licensed and registered dumps Principal Contractor is to supply the NLB Project Engineer with 'as-built' information for incorporation within NLB Operational and Maintenance documentation, which includes the Health and Safety file in line with current CDM Regulations. ******IMPORTANT NOTE******* SITE VISIT ON 15 AUGUST 2024 - PLEASE ADVISE ATTENDANCE BY 14 AUGUST 2024

Scope

Reference
BIP875932797
Total value
£1,000,000 excluding VAT
Commercial tool
Standalone contract
Contract dates
06 Oct 2024 to 14 Mar 2025
CPV classifications
31000000 45111100 63724400 45216128
Particular suitability
Small and medium-sized enterprises (SME)

Submission & procedure

Submission deadline
29 Aug 2024, 1:00 pm