Jonas Court Main Fit Out Works
Estimated value
£1.4m
Awarded value
£1.8m
Suppliers
1
Lots
1
Published
13 Jul 2017
Description
The works comprise the fit out works for the refurbishment of Jonas Court into a boutique student hotel. The stripping out of internal partition walls, forming new structural openings, removal of fixed furniture, sanitary ware and kitchen fixtures and fittings, removal of ceilings and removal of floor finishes as well as some stripping out of the existing mechanical and electrical services shall be undertaken during the enabling works package. The main works will comprise installation of the new services along with provision of new fixtures fittings and finishes. Upgrades to the external parking will also be required.
Scope
- Reference
- 1589/MR/2
- Total value
- £1,400,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 13 Mar 2017 to 06 Jul 2017
- CPV classifications
- 45214400
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 10 Feb 2017, 12:00 am
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£1.8m
Award date
14 Mar 2017
Contract start
13 Mar 2017
Contract end
06 Jul 2017