Mooring Line and Dynamic Cable Monitoring and Replacement Methodologies ORE/25/003

Offshore Renewable Energy CatapultcontractContracts FinderRef OREC001-DN762770-55873154SME suitableclosed
View buyer

Estimated value

£75k

Awarded value

Suppliers

0

Lots

1

0 awarded

Published

10 Feb 2025

Deadline 14 Mar 2025

Description

The O&M phase of a floating offshore wind farm will contain activities not previously required in fixed offshore wind, including the monitoring and replacement of mooring lines and dynamic cables. Little is currently known of component failure modes and risk profile, and the time and monetary costs of repair / replacement operations. Their impact on overall OPEX for floating wind farms is therefore not currently well understood.

Scope

Reference
OREC001-DN762770-55873154
Total value
£75,000 excluding VAT
Commercial tool
Standalone contract
Contract dates
13 Apr 2025 to 29 Jun 2026
CPV classifications
73000000
Particular suitability
Small and medium-sized enterprises (SME)

Submission & procedure

Submission deadline
14 Mar 2025, 12:00 pm