Provision of Whitehall Boiler Systems Relagging Project
Estimated value
£949k
Awarded value
£949k
Suppliers
1
Lots
1
Published
25 May 2021
Description
Government Property Agency (GPA) requires a Contractor to replace lagging to 2000m of pipework on the Whitehall Boiler System (WBS) during the "summer period" of April to September 2021. Net Zero is the UK Government's statutory target for at least a 100% reduction of UK Greenhouse Gas Emissions (GHG) by 2050, against 1990 levels. In June 2019, secondary legislation was passed that extended that target to "at least 100%". If met, this would effectively mean the UK would end its contribution to global emissions by 2050. According to the Committee on Climate Change's most recent report to Parliament, significant work is required to be undertaken for the UK to achieve its targets.
Scope
- Reference
- CCZG21A02.
- Total value
- £949,333.33 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 20 Apr 2021 to 19 Sept 2021
- CPV classifications
- 50000000 71000000
Submission & procedure
- Submission deadline
- 22 Mar 2021, 4:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£949k
Award date
19 Apr 2021
Contract start
20 Apr 2021
Contract end