2025-104 Major Projects Cost Assessment
Estimated value
£250k
Awarded value
£250k
Suppliers
1
Lots
1
Published
19 May 2026
Description
Accelerated Strategic Transmission Investment (ASTI) is a regulatory approval and funding framework for onshore transmission projects required to deliver the Government's 2030 Net Zero ambitions. It applies to 26 transmission projects with the aim to facilitate accelerated delivery. Large Onshore Transmission Investments (LOTI) assesses large electricity transmission projects that come forward during the RIIO-ET2 price control and potentially RIIO-3, period. Transmission Operators (TO's) submit applications under ASTI and LOTI for project assessment which are reviewed by Ofgem. Ofgem requires the support of a supplier to support on the Large Transmission Project Delivery Team (LPTD) with their ASTI and LOTI Project Assessments, in particular reviewing cost estimates and identifying potential areas of efficiency.
Scope
- Reference
- MT236312
- Total value
- £250,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 18 Dec 2025 to 30 Mar 2028
- CPV classifications
- 72224000 79400000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 16 Dec 2025, 5:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£250k
Award date
17 Dec 2025
Contract start
18 Dec 2025
Contract end
30 Mar 2028