Mobile Elevating Work Platforms (MEWPS) - Stage 2
Estimated value
£2.5m
Awarded value
—
Suppliers
1
Lots
1
Published
02 Jul 2021
Description
Bauer Keller JV have been awarded the Piling works for a Large project. These works commencing from Autumn 2020 until Winter 2024. Mobile Elevating Work Platforms will be required for this large project. Certificates must be provided with the equipment. BKJV may choose to use a balanced scorecard approach to its procurement activities. Suppliers will be assessed on various factors including, but not limited to, Quality, Safety, Experience, Adding Value. Small Medium Enterprises are actively encouraged within this Project and the promotion of innovation and sustainable working practices. Full details and specifications will be provided to the successfully shortlisted suppliers. Suppliers should take cognisance of the scale of this project and should carefully and realistically assess their internal capabilities to be able to carry out the intended scope of works. Bauer Keller is a Joint Venture formed from two of the World's Largest Specialist Geotechnical Contractors. The Joint Venture allows both companies to work together, providing a wealth of knowledge and experience, using proven, best practice techniques. We are committed to providing a safe and healthy working environment and we strive to deliver the highest standards, collaborating across disciplines to bring our customers consistently high performance in order to meet their needs.
Scope
- Reference
- C4A52293662
- Total value
- £2,500,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 01 Mar 2021 to 31 Mar 2024
- CPV classifications
- 34514700 45252110
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 27 Nov 2020, 12:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
—
Award date
01 Jul 2021
Contract start
01 Mar 2021
Contract end
31 Mar 2024