Replacement boilers at Yates Court
Estimated value
£163k
Awarded value
£163k
Suppliers
1
Lots
1
Published
30 Sept 2025
Description
Rooftop Housing Association Limited have awarded a contract to Hewer Facilities Management Limited to isolate, make safe, remove and replace boiler number 1 at the above location and then follow up with the same process in respect of boilers number 2 and 3. Includes installation of a Siemens Synco cloud-based remote access system. A full commissioning and heat testing of the new boilers and controls to then be undertaken by the boiler manufacturer and boiler controls specialist. Contract was procured via a Request for Quotes - tenders requested via email from a closed group of local, pre-selected suppliers. Contract period is from 14 July 2025 to 20 October 2025. If you have any questions regarding this award, please email procurement@rooftopgroup.org
Scope
- Reference
- RHA_YATES_BOILERS
- Total value
- £163,147.38 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 13 Jul 2025 to 19 Oct 2025
- CPV classifications
- 45350000
- Particular suitability
- Small and medium-sized enterprises (SME)Voluntary, community and social enterprises (VCSE)
Submission & procedure
- Submission deadline
- 09 May 2025, 4:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£163k
Award date
26 May 2025
Contract start
13 Jul 2025
Contract end