Principal Designer Service Provision Requirement
Estimated value
£9k
Awarded value
£9k
Suppliers
1
Lots
1
Published
08 Mar 2018
Description
Plan, manage, monitor and coordinate health and safety in the pre-construction phase. In doing so they must take account of relevant information (such as an existing health and safety file, asbestos records etc.) that might affect design work carried out both before and after the construction phase has started. Help and advise the YHN (The Client) in bringing together pre-construction information (PCI), and provide the information designers and contractors need to carry out their duties. Work with YHN and the Principal Contractor designers throughout the full design phase appraising designs on the project to eliminate foreseeable health and safety risks to anyone affected by the work, or in the occupying/running/maintenance of the completed building and, where that is not possible, take steps to reduce or control those risks. Ensure that everyone involved in the pre-construction phase communicates and cooperates, coordinating their work wherever required. Liaise with the principal contractor, keeping them informed of any risks that need to be controlled during the construction phase.
Scope
- Reference
- HRA-P1644
- Total value
- £9,375 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 22 Jan 2018 to 26 Jul 2018
- CPV classifications
- 45000000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 03 Jan 2018, 12:00 am
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£9k
Award date
15 Jan 2018
Contract start
22 Jan 2018
Contract end
26 Jul 2018