Description
The present report aims to clarify the geometrical construction tolerances required in the construction of the Precast Segmental Viaducts. It applies to all components that constitute the said assets and should be implemented in design and construction. The list of assets to which this document applies to is as follows: - Water Orton 1 and 2 Viaducts - River Tame West Single Track - River Tame West Double Track Viaduct - River Tame East Viaduct
Scope
- Reference
- C4N87443335
- Total value
- £150,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 31 Mar 2025 to 31 Dec 2026
- CPV classifications
- 43320000 44000000
Submission & procedure
- Submission deadline
- 21 Nov 2024, 6:00 pm