M4 Junction 16 Improvements Scheme

Swindon Borough CouncilcontractContracts FinderRef BIP218997012complete
View buyer

Estimated value

£11.0m

Awarded value

£11.0m

Awarded 11 Sept 2016

Suppliers

1

Lots

1

1 awarded

Published

02 Oct 2016

Deadline 11 Sept 2016

Description

Improvement of M4 Junction 16. The work consists of: Creating a right hand turn for Swindon traffic turning onto Hays Lane using one signalised junction. Constructing a new signalised junction for traffic joining Hay Lane from J16. Widening the M4 westbound and eastbound off-slip to four lanes. Widening the circulation carriageway on the Great Western Way approach, and suitable modifications to all other junction approaches. Modifying and relocating road signage, road markings and surface water drainage systems to suit the final carriageway location and configuration. The contract is expected to take 3 years including the construction and maintenance period.

Scope

Reference
BIP218997012
Total value
£11,000,000 excluding VAT
Commercial tool
Standalone contract
Contract dates
12 Sept 2016 to 16 Feb 2019
CPV classifications
45000000

Submission & procedure

Submission deadline
11 Sept 2016, 11:00 pm

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£11.0m

Award date

11 Sept 2016

Contract start

12 Sept 2016

Contract end