BBV HS2 MWCC North - Deep Drainage - Micro Tunnelling (WP/CM)

BIP SOLUTIONS LIMITEDcontractContracts FinderRef C4A54714497complete
View buyer

Estimated value

£1

Awarded value

£3.8m

Awarded 23 Nov 2021

Suppliers

1

Lots

1

1 awarded

Published

22 Dec 2022

Deadline 08 Apr 2021

Description

Balfour Beatty VINCI (BBV) have been awarded HS2 main works civils contracts, lots N1 and N2. We are looking to engage with the supply chain whom provide Deep Drainage/ Micro Tunnelling works. This package of works includes two pipeline runs to be installed. The two pipes are different in diameter, one being 600mm & the other is a 1500 mm. The length of 1500 mm pipe featured is approximately 1190 metres. The peak depth of the install features at 11.90 metres BGL. A 600 mm pipe is also featured and this will also convey waters between the Marston Lane inlet, to an outlet planned at the rear of the Kingsbury Compound settlement pond. Full details and specifications will be provided to the successfully shortlisted suppliers. Suppliers should be aware of the scale of this project and should assess their internal capabilities to be able to carry out the intended scope of works, prior to completing this expression of interest (EOI).

Scope

Reference
C4A54714497
Total value
£1 excluding VAT
Commercial tool
Standalone contract
Contract dates
27 Jul 2021 to 30 Mar 2022
CPV classifications
43120000 43300000 43614000 45000000

Submission & procedure

Submission deadline
08 Apr 2021, 1:00 pm

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£3.8m

Award date

23 Nov 2021

Contract start

27 Jul 2021

Contract end

30 Mar 2022