PUP Feasibility Study
Estimated value
£451k
Awarded value
£451k
Suppliers
1
Lots
1
Published
26 Nov 2024
Description
The services are Feasibility and Early Contractor involvement. The key scope activities for this package include: o Developing options for the upgrade of existing substations and traction power cable sections; o Carrying out desktop and on-site surveys, including, at a high level: on site comparisons with existing data of substations, condition assessments and ground investigation; o Establishing the assessment criteria to enable options to be considered; o Contractor involvement in the consideration of constructability and logistics, followed by the production of an updated project cost estimate for the SPO; o Consideration of environmental / sustainability issues and opportunities.
Scope
- Reference
- CW68025
- Total value
- £450,989 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 15 Oct 2024 to 26 Jun 2026
- CPV classifications
- 71300000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 14 Oct 2024, 11:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£451k
Award date
14 Oct 2024
Contract start
15 Oct 2024
Contract end
26 Jun 2026