Design, Build & Project Management of New Shotton Community Centre
Estimated value
£60k
Awarded value
£65k
Suppliers
1
Lots
1
Published
03 Aug 2018
Description
New Shotton Community Centre Design & Project Management Brief Shotton Parish Council have been successful in obtaining Big Lottery Funding towards the design and build of a new purpose-built community centre in the village of Shotton Colliery. Accordingly, tenders are required from suitably qualified building professionals to undertake work from RIBA Stage 3 (Developed Design); RIBA Stage 4 (Technical Design and Tendering) and including RIBA Stages 5&6 (Construction to Handover) for a new purpose-built Community Centre in Shotton. In addition, fulfil the requirements of the funding bodies, particularly the Big Lottery Fund. Project Objectives The objective of the project is to provide a friendly accessible community centre which is at the heart of the community in Shotton. Situated adjacent to the existing Community Centre, the new building will be light, welcoming, energy efficient and easy to manage and maintain. The Site The site is next to the existing Shotton Community Centre as shown on the attached plan and is owned by Shotton Parish Council. The Client The Client is Shotton Parish Council; the main contact for the project is the Clerk of the Council Stuart Wardle. A working group has been established to work with the lead building professional on every aspect of the development of the project. Current Position A concept design, based on an agreed schedule of accommodation, has been prepared by D3 Associates Ltd. The design was part of a successful Stage 1 BLF Reaching Communities Building Programme bid. Approval has been granted to proceed to the construction phase providing the project is within budget and all funding in place. The budget cost for the new building, including external works, utility services and demolition of the existing community centre is £735K. A pre-application has been submitted to Durham County Council, a full planning application is to be prepared and submitted on completion of RIBA Stage 3. Submission of tender documents Tenders will be evaluated on quality, price and value for money. As part of the quality element, we will look at: • Understanding of the aims and requirements of the project • Quality and content of the submission • Experience of similar community-based projects • Experience or working with Big Lottery capital funded projects • Qualifications and experience of staff allocated to this project • Approach and methodology • Ideas on making our building environmentally sustainable • Ideas on minimising capital costs • Ideas on minimising running costs • Timescales for delivery of commission. Please submit your tender document, including the completion of the fee schedule included in the attached Brief in a plain envelope headed Tender Brief for Shotton Community Centre to be received by noon on 15th June 2018 to: The Clerk of Shotton Parish Council, 14 Claypool Farm Close, Hutton Henry, Hartlepool TS27 4QZ Email: wardlestuart@btinternet.com
Scope
- Reference
- SW/SPC/COMMCENTRE 2018
- Total value
- £60,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 21 Jun 2018 to 29 Sept 2019
- CPV classifications
- 71200000 71300000 71400000 71500000 71600000 71700000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 14 Jun 2018, 11:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£65k
Award date
24 Jun 2018
Contract start
21 Jun 2018
Contract end
29 Sept 2019