The design, construction, installation and commissioning of a bespoke designed dual fuel furnace
Estimated value
£450k
Awarded value
£525k
Suppliers
1
Lots
1
Published
13 Jan 2025
Description
The design, construction, installation and commissioning of a bespoke designed dual fuel furnace with specific adaptions for enhanced data collection to facilitate the modelling of furnace temperature distributions during operation and to monitor changes to the product in the furnace during the heating and cooling cycles. Interested parties are to contact procurement@uk.lucideon.com to register their interest and will be provided a copy of the ITT and a PQQ for completion. If you have any questions or comments in relation to this tender, they must be submitted to procurement@uk.lucideon.com Completed tenders must be submitted to procurement@uk.lucideon.com
Scope
- Reference
- LUC0015
- Total value
- £450,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 09 Dec 2024 to 30 Mar 2025
- CPV classifications
- 42300000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 08 Nov 2024, 3:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£525k
Award date
10 Jan 2025
Contract start
09 Dec 2024
Contract end
30 Mar 2025
Awarded suppliers· 1 supplier
Awarded 10 Jan 2025 · Contract period 09 Dec 2024 — 30 Mar 2025
Other contracts from LUCIDEON LIMITED
Full notice and award history for this contracting authority is on the buyer profile.
Other contracts awarded to Therser UK LTD· 7
Cross-buyer view of this supplier's public-sector wins.
| Title | Type | Value | Published |
|---|---|---|---|
| 4855/AMRC/GM/2025 Kiln Modification for Hydrogen / Natural Gas Mix R2 | contract | — | 30 Mar 2026 |
| 4855/AMRC/GM/2025 Kiln Modification for Hydrogen / Natural Gas Mix R2 | contract | — | 15 Dec 2025 |
| The design, construction, installation and commissioning of a bespoke designed dual fuel furnace. | contract | — | 13 Jan 2025 |
| Upgrade to existing Natural Gas Roller Hearth Tile Kiln to fire on 100% Hydrogen | contract | — | 01 Dec 2023 |
| Upgrade to existing High Temperature Intermittent Kiln to fire on 100% Hydrogen | contract | — | 23 Nov 2023 |
| Upgrade to existing High Temperature Intermittent Kiln to fire on 100% Hydrogen | call off | £272k | 23 Nov 2023 |
| Payment for an innovation grant on an ERDF project (Aerospace UP), SE45B3 | contract | £32k | 16 Jun 2022 |