The design, construction, installation and commissioning of a bespoke designed dual fuel furnace.
Estimated value
—
goods
Awarded value
—
Suppliers
1
1 SME
Lots
1
1 awarded
Published
13 Jan 2025
Description
The design, construction, installation and commissioning of a bespoke designed dual fuel furnace with specific adaptions for enhanced data collection to facilitate the modelling of furnace temperature distributions during operation and to monitor changes to the product in the furnace during the heating and cooling cycles.
Scope
- Reference
- ocds-h6vhtk-04a6a5
- Commercial tool
- Standalone contract
- Contract dates
- 09 Dec 2024 to —
- Main category
- goods
- Contract locations
- West Midlands
Award criteria
Criteria the buyer will use to evaluate bids.
| Name | Description | Type | Weighting |
|---|---|---|---|
| Cost / financial | 25% | cost | — |
Submission & procedure
- Procedure
- Open procedure
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
—
Award date
—
Contract start
—
Contract end
—
Awarded to
Awarded suppliers· 1 supplier
Awarded —
Award value
—
Other contracts from LUCIDEON LIMITED
Full notice and award history for this contracting authority is on the buyer profile.
Other contracts awarded to Therser UK· 7
Cross-buyer view of this supplier's public-sector wins.
| Title | Type | Value | Published |
|---|---|---|---|
| 4855/AMRC/GM/2025 Kiln Modification for Hydrogen / Natural Gas Mix R2 | contract | — | 30 Mar 2026 |
| 4855/AMRC/GM/2025 Kiln Modification for Hydrogen / Natural Gas Mix R2 | contract | — | 15 Dec 2025 |
| The design, construction, installation and commissioning of a bespoke designed dual fuel furnace | call off | £525k | 13 Jan 2025 |
| Upgrade to existing Natural Gas Roller Hearth Tile Kiln to fire on 100% Hydrogen | contract | — | 01 Dec 2023 |
| Upgrade to existing High Temperature Intermittent Kiln to fire on 100% Hydrogen | contract | — | 23 Nov 2023 |
| Upgrade to existing High Temperature Intermittent Kiln to fire on 100% Hydrogen | call off | £272k | 23 Nov 2023 |
| Payment for an innovation grant on an ERDF project (Aerospace UP), SE45B3 | contract | £32k | 16 Jun 2022 |