G4_3_HCC_003 Botley Bypass
Estimated value
£20.3m
Awarded value
£20.3m
Suppliers
1
Lots
1
Published
14 Oct 2022
Description
A call-off from the Generation 4-THREE 2020 - 2024 Civil Engineering, Highways and Transportation Collaborative Framework (Awarded November 2019). The works will consist of: - Early Contractor Involvement (using NEC4 ECC Secondary Option X22) for producing documents to discharge planning conditions and environmental permissions, advice on buildability and sequencing, undertake contractor design elements, build the target and develop the construction programme - Construction of a 1.8km bypass and 3m wide footway and cycleway - Construction of a new bridge over the River Hamble - Construction of a new roundabout to replace the existing A335/A3051 priority junction - Associated drainage works.
Scope
- Reference
- ET19648
- Total value
- £20,316,420.29 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 28 Aug 2022 to 30 May 2025
- CPV classifications
- 45220000 45230000
Submission & procedure
- Submission deadline
- 22 Jul 2022, 1:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£20.3m
Award date
17 Aug 2022
Contract start
28 Aug 2022
Contract end
30 May 2025