Northstowe Phase 2: Highway and Infrastructure Works
Estimated value
£48.9m
Awarded value
£48.9m
Suppliers
1
Lots
1
Published
16 Nov 2017
Description
The HCA is proposing to undertake the construction of highways and infrastructure works at our Northstowe site, 10 km North West of Cambridge. See section II.2.4 for further details. Additional CPV codes include 45111000: Demolition, site preparation and clearance work and 65000000: Public utilities.
Scope
- Reference
- BIP285469075
- Total value
- £48,938,665 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 26 Oct 2017 to 31 Oct 2019
- CPV classifications
- 45233100
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 28 Sept 2017, 11:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£48.9m
Award date
28 Sept 2017
Contract start
26 Oct 2017
Contract end
31 Oct 2019
Awarded suppliers· 1 supplier
Awarded 28 Sept 2017 · Contract period 26 Oct 2017 — 31 Oct 2019
Other contracts from Homes & Communities Agency
Full notice and award history for this contracting authority is on the buyer profile.
Other contracts awarded to John Sisk and Son (Holdings) Ltd· 6
Cross-buyer view of this supplier's public-sector wins.
| Title | Type | Value | Published |
|---|---|---|---|
| YORcivil Major Works 2 Contractors Framework Agreement | contract | — | 11 Nov 2025 |
| A59 Kex Gill Diversion | contract | £50.8m | 03 Oct 2022 |
| YORcivil Major Works Contractors Framework Agreement | contract | £250.0m | 06 Feb 2020 |
| M6 Junction 10 Improvement Scheme | contract | £39.2m | 05 Aug 2019 |
| CM122 YORcivil 2 North and East Area Contractors Framework Agreement | contract | £13.5m | 23 Jan 2018 |
| Spigot Repair Works - Liverpool Cruise Liner Terminal | contract | £1.2m | 19 Apr 2017 |