Gable Grade11* listed prep & repainting high level steel work 052-2020

Manchester City CouncilcontractContracts FinderRef MANC001-DN465442-81992077SME suitablecomplete

Estimated value

£250k

Awarded value

£250k

Awarded 31 Mar 2020

Suppliers

1

Lots

1

1 awarded

Published

23 Feb 2021

Deadline 31 Mar 2020

Description

Manchester Central are currently looking for a competent Contractor to carry out the repainting of high-level structural steel and wrought iron to the two gable ends of a Grade II* listed English Heritage building in the heart of Manchester. The Contract period will be dependent on products used; initial estimate of works is to be completed within 20-26 weeks. It is intended for the contract to commence on approx. 15th April 2020. The requirement of this project is to carry out the above-mentioned works to the Front and Rear Gable, with the Front Gable being undertaken at an estimated date of Spring 2022. Manchester Central does not expect the activities to impact the day to day operations of the venue or events in tenancy and will work closely with the contractor to ensure effective delivery. If it is deemed to impact the business and/or events Manchester Central reserve the right to decline access to the gables, and to arrange for the works to be undertaken at an alternate time. The technical specification, within Appendix 2 of this document, gives the technical requirements for the re-painting of the steel and wrought iron surfaces of the two gable end structures at Manchester Central. The specification provides technical requirements for: • Surface preparation of steel and wrought iron surfaces with existing paints in various conditions of degradation; • Requirements for paints type for use in the re-painting works; • Requirements for testing and paint trials prior to commencement of the works; • Requirements for Quality Management and Quality control of surface preparation and painting of the gable end structures. The Gable End structures are part of a Grade II* listed building and the Contractor shall comply with any conservation or heritage or planning requirements for the structure. The Contractor is also responsible the design, specification and provision of safe working access to the structure.

Scope

Reference
MANC001-DN465442-81992077
Total value
£250,000 excluding VAT
Commercial tool
Standalone contract
Contract dates
22 Apr 2020 to 29 Oct 2020
CPV classifications
50000000
Particular suitability
Small and medium-sized enterprises (SME)

Submission & procedure

Submission deadline
31 Mar 2020, 12:00 pm

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£250k

Award date

31 Mar 2020

Contract start

22 Apr 2020

Contract end

29 Oct 2020