Anson House and Hudson House, Thornaby - Replacement of Boosted Cold Water System
Estimated value
£110k
Awarded value
—
Suppliers
0
Lots
1
Published
20 Oct 2017
Description
Thirteen Housing Group (THG) requires a company to carry out the following work/s: The work comprises the isolation and removal of the obsolete cold water storage and booster pump set. Temporary installation of a potable cold water storage tank & new booster pump set complete with pipework/insulation/ standalone controls and pipework modifications with control valves. Installation of a new GRP cold water storage tank & relocate new booster set complete with controls/electrical work/minor structural & builders work installation/ pipework modifications with control valves/gauges filters etc. The existing plant room doors are to be renewed. All work carried out must comply with Gas Safety (installation and use) Regulations 1998 and BS 7671 (IET Wiring Regulations).
Scope
- Reference
- THIR/TEN/17/491
- Total value
- £110,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 01 Dec 2017 to 28 Feb 2018
- CPV classifications
- 42122130 44611500
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 10 Nov 2017, 12:00 am