Fit Out - Lift Steelwork & Glazing -WP12.2.1 - Old Oak Common (S4) Station

Balfour Beatty VINCI Systra JVcontractContracts FinderRef C4N70243081SME suitableclosed

Estimated value

£20.0m

Awarded value

Suppliers

0

Lots

1

0 awarded

Published

19 Apr 2023

Deadline 01 May 2023

Description

WP12.2.1 - HS2 Lift Steelwork & Glazing Scope of Work: The OOC Station HS2 Scenic Lifts Fit Out package consists of the primary steelwork and cladding to the OOC HS2 station scenic lifts and comprises of the following scope: • Detailed design, supply and installation of primary steelwork and glazed cladding to 12 scenic + 3 interchange lifts in the HS2 station platforms and concourse area, including provision of brackets, supports and required service holes to interfacing contractors. • Fully coordinated design with MEPH services, advertising, signage, station common components and lifts contractor, including design of brackets, supports and allowance for service holes. • Provide RIBA 5 design and construction drawings including connection details, fabrication drawings, general arrangements, and elevation drawings for construction.

Scope

Reference
C4N70243081
Total value
£20,000,000 excluding VAT
Commercial tool
Standalone contract
Contract dates
30 Jun 2024 to 30 Mar 2028
CPV classifications
42416100 45262670 45441000 45210000 45223100 39299200 45223110
Particular suitability
Small and medium-sized enterprises (SME)

Submission & procedure

Submission deadline
01 May 2023, 7:00 am