RECONSTRUCTION OF COVENTRY FIRE STATION

West Midlands Fire ServicecontractContracts FinderRef C002115SME suitableVCSE suitablecomplete

Estimated value

£6.5m

Awarded value

£6.5m

Awarded 22 May 2016

Suppliers

1

Lots

1

1 awarded

Published

25 Jul 2016

Deadline 05 Apr 2016

Description

The contract scope includes working with the design team to develop the design and cost model in a pre-construction period. During this period the Contractor will be required to procure temporary accommodation to create a temporary fire station on the site, assist in the decant of the fire station and subsequently demolish the existing property. On completion of the demolition construction of the new fire station will take place. After the construction period is completed the Contractor will assist in the decant from the temporary fire station and will remove the temporary buildings. This contract was awarded using using the Constructing West Midlands Framework Agreement; Lot 7

Scope

Reference
C002115
Total value
£6,500,000 excluding VAT
Commercial tool
Standalone contract
Contract dates
21 May 2016 to 31 Dec 2017
CPV classifications
45216000
Particular suitability
Small and medium-sized enterprises (SME)Voluntary, community and social enterprises (VCSE)

Submission & procedure

Submission deadline
05 Apr 2016, 11:00 pm

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£6.5m

Award date

22 May 2016

Contract start

21 May 2016

Contract end