G5-1_HCC_032 Parallel Crossing East near Havanah Way, Bordon - Main Works
Estimated value
£78k
Awarded value
£78k
Suppliers
1
Lots
1
Published
09 Aug 2024
Description
A call-off from Lot 1 of the Generation 5 Civil Engineering, Highways & Transportation Collaborative Framework 2024 - 2028 (awarded 16 January 2024). Installation of a new parallel crossing on Budds Lane in Borden. This comprises of new carriageway resurfacing for approximately 230 sq. meters. With zig zag markings approx. 22m length. new footway construction either side of the crossing including tactile paving south side approx. 22 sq. meters and north side is approx. 18 sq. meters. New orange flashing beacons to be present at either side of the crossing.
Scope
- Reference
- UN24742
- Total value
- £78,379.66 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 04 Jul 2024 to 27 Aug 2024
- CPV classifications
- 45230000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 27 Jun 2024, 1:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£78k
Award date
04 Jul 2024
Contract start
04 Jul 2024
Contract end