UK SBS CON16016 Design & Construction of a Data Centre, Fajara, The Gambia
Estimated value
£900k
Awarded value
£713k
Suppliers
1
Lots
1
Published
25 Jan 2017
Description
Project Scope The project is concerned with the design and construction of the new Data Center at the MRC The Gambia site in Fajara. The project consists of two distinct phases: Phase A – the design of the facility, Phase B – construction and commissioning of the facility. Phase A will inform a business case with which the funding for the phase B is sought to be secured. The MRC will reserve the right to proceed to Phase B with the successful bidder at a later point (no later than 2 years after design completion) or not to proceed at all without being liable to compensation to the successful bidder.The need for a new Data Centre is critical for the continuation and expansion of the research work the Unit carries out in The Gambia. The facility needs to be sufficient to cater for High-Performance Computing (HPC) for Genomics, future expansion in data processing and storage, including the support of a Laboratory Information Management System (LIMS) which the Unit is to procure/implement in this year. The design must also allow efficiency in energy consumption, best possible insulation, and generally good suitability for the local climate.
Scope
- Reference
- UK SBS CON16016 Design & Construction of a Data Centre, Fajara, The Gambia/2
- Total value
- £900,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 18 Nov 2016 to 30 Mar 2017
- CPV classifications
- 45000000 71500000
Submission & procedure
- Submission deadline
- 26 Oct 2016, 11:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£713k
Award date
21 Nov 2016
Contract start
18 Nov 2016
Contract end
30 Mar 2017