Central Cycle Hub Construction

UNIVERSITY OF SHEFFIELDcontractContracts FinderRef 1571/MR/2SME suitableVCSE suitablecomplete
View buyer

Estimated value

£250k

Awarded value

£555k

Awarded 06 Feb 2017

Suppliers

1

Lots

1

1 awarded

Published

13 Jul 2017

Deadline 23 Jan 2017

Description

Tender Opportunity 1571/MR The University wishes to install a cycle hub on a sloping site that has electric cables underneath as well as pockets of asbestos materials identified in the site survey. The proposal is for 168 gas operated cycle storage racks along with Male and Female changing areas with showers,lockers, a disabled toilet and cleaners cupboard. The structure of the building is blockwork with render finish and a galvanised steel mesh finish. The University would like the contractor to explore economical methods to achieving the mesh finish to the front elevation but still achieving 30-40years life cycle costs This is an open Non EU procurement procedure. The ITT including full specification can be downloaded by registering (free of charge) and expressing your interest on the University's e-tendering system https://in-tendhost.co.uk/Sheffield. Completed tenders must be returned through the same e-tendering system. If you have any questions or comments in relation to this tender they must be submitted via the Intend System, this can be accessed at https://in-tendhost.co.uk/Sheffield The closing date for return of tenders is 12 noon on 23 January 2017 (UK time).

Scope

Reference
1571/MR/2
Total value
£250,000 excluding VAT
Commercial tool
Standalone contract
Contract dates
02 Apr 2017 to 31 Aug 2017
CPV classifications
45214400
Particular suitability
Small and medium-sized enterprises (SME)Voluntary, community and social enterprises (VCSE)

Submission & procedure

Submission deadline
23 Jan 2017, 12:00 am

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£555k

Award date

06 Feb 2017

Contract start

02 Apr 2017

Contract end

31 Aug 2017